L-550 Rock Creek Drainage

Langdon, Missouri

CLIENT

JJ Westhoff Construction

OWNER

United States Army Corps of Engineers

PROJECT REVENUE

$209K

TIME

2021-2022

D.CaseStudies L550 Rock Creek Drainage Web
GRIFFIN DIFFERENCE

Griffin had previously completed several other structures very similar in size and scope in the area, so Griffin was able to turn around a bid and subsequent submittal quickly. The USACE representatives on this project were especially attentive to detail. With Griffin’s past experience we were able to get the USACE exactly what they needed to get the work approved.

Once approved, Griffin had a very short schedule to install and pull together manpower, equipment, and materials. Not only did Griffin accomplish this in a short time frame, but Griffin delivered a successful dewatering system that dried up the site as designed.

THE CHALLENGE

The work for this fast tracked project took place in an existing drainage ditch that needed to remain in use during construction activities. The area was also surrounded by existing levees and was in close proximity to existing relief wells. The dewatering wells had to be located such that they were not in the levee toe or within 40 ft. of an existing relief well.

THE SOLUTION

The general contractor had to competitively seek out qualified bidders to handle the dewatering efficiently and effectively. Griffin’s plan was ultimately selected for being the most responsive, complete, and capable bid, even though it was not the lowest cost. Griffin’s design consisted of deep wells, a dual generator system with auto switch gear, and telemetry to remotely determine flows and notify the team in case of generator failure or a decrease in groundwater flow.

CALCULATOR

DEWATERING ADVISOR

Enter your excavation information to learn about options and considerations for selecting dewatering systems.

CASE STUDIES

VIEW RELATED POSTS

Santa Ana Mainstream-Reach 9
Santa Ana Mainstream-Reach 9
Learn How >
West Refueler and Solid Waste Facility
West Refueler and Solid Waste Facility
Learn How >
Alexan Old Town Project
Alexan Old Town Project
Learn How >
Port Covington
Port Covington
Learn How >
929 Zurich Circle
929 Zurich Circle
Learn How >
L-611 Drainage Structure
L-611 Drainage Structure
Learn How >
Fort Eustis Sump Pit Structure
Fort Eustis Sump Pit Structure
Learn How >
Chesapeake City WWTP
Chesapeake City WWTP
Learn How >
Decatur School Annex
Decatur School Annex
Learn How >