Brazoswood Athletic-High School

Clute, Texas

CLIENT

Stewart Builders

ENGINEER

Matrix Structural Engineers

REVENUE

$75,000

TIME

2020

D.CaseStudies Brazoswood final

Griffin installed the dewatering system in a timely manner and the contractor was able to maintain their schedule because the dewatering system kept groundwater under control. Griffin provided weekly monitoring of the dewatering system and fuel service throughout the project to ensure that the system was operating properly.

THE CHALLENGE

Lowering groundwater 17ft. below ground surface for an excavation of approximately 550 ft. x 100 ft. The new building foundation was connected to an existing building which limited room to install the dewatering system.

THE SOLUTION

A wellpoint dewatering system approximately 550 ft. long was installed parallel to the existing building.

Griffin installed 80 wellpoints at an approximate spacing of 7 ft. to a depth of 30 ft. We provided one operating and one standby wellpoint pumpto operate the system.

The pumps were plumbed to a 500-gallon fuel tank that provided almost one week of run time between fueling.

CALCULATOR

DEWATERING ADVISOR

Enter your excavation information to learn about options and considerations for selecting dewatering systems.

CASE STUDIES

VIEW RELATED POSTS

Santa Ana Mainstream-Reach 9
Santa Ana Mainstream-Reach 9
Learn How >
West Refueler and Solid Waste Facility
West Refueler and Solid Waste Facility
Learn How >
Alexan Old Town Project
Alexan Old Town Project
Learn How >
Port Covington
Port Covington
Learn How >
929 Zurich Circle
929 Zurich Circle
Learn How >
L-611 Drainage Structure
L-611 Drainage Structure
Learn How >
Fort Eustis Sump Pit Structure
Fort Eustis Sump Pit Structure
Learn How >
Chesapeake City WWTP
Chesapeake City WWTP
Learn How >
Decatur School Annex
Decatur School Annex
Learn How >