The Driscoll at River Oaks High-Rise

Houston, Texas

OWNER

Weingarten Realty Investors

GC

Hanover RS Construction LLC

ENGINEER

Brown and Gray Engineers, Inc.

TIME

2018-2020

REVENUE

$200,000

D.CaseStudies Driscoll Project Rig
GRIFFIN DIFFERENCE

We addressed the extremely deep excavation by designing a deep well dewatering system capable of lowering groundwater more than 30 ft. below grade. The system was installed at the perimeter of the excavation prior to work beginning in the excavation. This ensured that the dewatering effort had minimal impact to excavation work and schedule. The contractor was able to maintain their schedule because the dewatering system is kept groundwater under control.

THE CHALLENGE

The project consisted of the construction of a 30-story high-rise building with 2 levels of below grade parking. The deepest subgrade (approximately ±30 ft. below grade) extended to a depth below the water table (which sat approximately 16.5 ft. below grade). An engineered dewatering solution was required to lower groundwater below the proposed excavation.

THE SOLUTION

Griffin installed a deep well dewatering system to assist in control of groundwater to allow construction to be conducted in a safe and efficient manner. Twenty (20) wells were drilled surrounding the shored excavation. Griffin also installed a piezometer at each deep well to monitor water levels All wells and piezometers were drilled to a depth of ±70 ft. and were completed with well screen, casing, and gravel pack. Griffin also furnished and installed a well pump system consisting of twenty (20) each 1.0 to 2.0hp, 460v/3 phase electric submersible pumps. Each pump was equipped with valves/fittings and on grade electrical distribution. Griffin provided the electric wiring to the pump control panels at each well location. Effluent from each well was directed through a common manifold (approximately ±800 ft.) to the designated discharge point. The total flow for the deep well dewatering system was approximately 250 GPM.

CALCULATOR

DEWATERING ADVISOR

Enter your excavation information to learn about options and considerations for selecting dewatering systems.

CASE STUDIES

VIEW RELATED POSTS

Santa Ana Mainstream-Reach 9
Santa Ana Mainstream-Reach 9
Learn How >
West Refueler and Solid Waste Facility
West Refueler and Solid Waste Facility
Learn How >
Alexan Old Town Project
Alexan Old Town Project
Learn How >
Port Covington
Port Covington
Learn How >
929 Zurich Circle
929 Zurich Circle
Learn How >
L-611 Drainage Structure
L-611 Drainage Structure
Learn How >
Fort Eustis Sump Pit Structure
Fort Eustis Sump Pit Structure
Learn How >
Chesapeake City WWTP
Chesapeake City WWTP
Learn How >
Decatur School Annex
Decatur School Annex
Learn How >