Block 58 Skyscraper Project

Houston, Texas

OWNER

Hines

TIME

2018- 2019

D.CaseStudies Block 58 Houston TX Web
GRIFFIN DIFFERENCE

Griffin provided a solution that minimized impact on construction access to a very
tight project site. Griffin’s discharge pipe was suspended above construction grade
from the excavation walls to maximize site access. Griffin proposed a solution under a minimum plus model. We mobilized with the plan of putting in the system that we believed would be sufficient if the site assumptions that were made were accurate. We provided a cost for additional wells (if needed) to create an equitable risk share with regard to the dewatering efforts.

THE CHALLENGE

An excavation of significant depth (30+ feet) in downtown Houston was challenged by hydrostatic uplift pressure. The site had only one access point and use of space was a continual concern. The main slab of the foundation could not be poured without dewatering and relieving the hydrostatic pressure. prevent the pumping of fines from the wells.

THE SOLUTION

Griffin provided groundwater management for the construction of the deep
foundation. Griffin installed 8 deep wells from 25 ft. below grade to relieve artesian
pressure in underlying sand. Wells were drilled to approximately 50 ft. below working grade by bucket auger and connected to a discharge header suspended from the excavation walls to maximize Gilbane’s access to the site. Griffin completed the system with several mobilizations to fit the clients schedule for needing to access the site.

CALCULATOR

DEWATERING ADVISOR

Enter your excavation information to learn about options and considerations for selecting dewatering systems.

CASE STUDIES

VIEW RELATED POSTS

Westminster Sewer Improvements Project
Westminster Sewer Improvements Project
Learn How >
West Refueler and Solid Waste Facility Project
West Refueler and Solid Waste Facility Project
Learn How >
University of Nebraska-Kiewit Hall Project
University of Nebraska-Kiewit Hall Project
Learn How >
The Yards Parcel I Project
The Yards Parcel I Project
Learn How >
The Driscoll at River Oaks High-Rise Project
The Driscoll at River Oaks High-Rise Project
Learn How >
Texas Medical Center Project
Texas Medical Center Project
Learn How >
St. Joseph Hospital Expansion Project
St. Joseph Hospital Expansion Project
Learn How >
SLC Airport Central Tunnel Project
SLC Airport Central Tunnel Project
Learn How >
Seabrook Gate Complex, CMAR Project
Seabrook Gate Complex, CMAR Project
Learn How >
Saylorville Lake/Big Creek Dam Project
Saylorville Lake/Big Creek Dam Project
Learn How >