Seabrook Gate Complex, CMAR Project

New Orleans, Louisiana

CLIENT

Alberici Constructors, Inc.

OWNER

USACE New Orleans District

PROJECT REVENUE

$2.3M

TIME

2010-2012

D.CaseStudies SeabrookPhoto 1
GRIFFIN DIFFERENCE

These solutions eliminated the need for the more expensive tremie slab method. These VE concepts saved USACE $16M with a 3-month schedule reduction from the critical path and provided temporary flood protection during construction, allowing USACE to achieve their congressionally-mandated intermediate milestone requirement for 100-year perimeter flood protection. Dewatering was performed with 42 deepwells with unwatering and rewatering pumps. personnel, Griffin achieved the required drawdown and treated for required VOCs and TSS and met the client’s needs.

THE CHALLENGE

Design and oversight of a dewatering system for the construction of a new levee wall system, vertical lift gates, and sector gates within the New Orleans IHNC. The biggest challenge to the project was a scour hole that extended to ±EL-87 caused by a previous bridge pier that crossed Navigation Canal.

THE SOLUTION

Installation of 42 deepwells, unwatering system, rewatering system, and operation and maintenance for project crossing Navigation Canal. Alberici conceptualized several accepted innovations during pre-construction that reduced risks and project costs during construction, including a temporary rock dike across the canal that reduced tidal flow to allow for use of a cofferdam and design/build dewatering system. The contractor backflled the scour hole with SP Sandy Soils and Griffin jetted deep wells that extended up to 75 ft. deep in the canal section of the project. This allowed for a subgrade of EL -28 to be achieved.

CALCULATOR

DEWATERING ADVISOR

Enter your excavation information to learn about options and considerations for selecting dewatering systems.

CASE STUDIES

VIEW RELATED POSTS

Mill Creek Diversion Chamber Project
Mill Creek Diversion Chamber Project
Learn How >
Westminster Sewer Improvements Project
Westminster Sewer Improvements Project
Learn How >
Airport Expansion PFAS Treatment Project
Airport Expansion PFAS Treatment Project
Learn How >
Antero Dam and Reservoir Project
Antero Dam and Reservoir Project
Learn How >
Petmin Pig Iron Plant Project
Petmin Pig Iron Plant Project
Learn How >
St. Joseph Hospital Expansion Project
St. Joseph Hospital Expansion Project
Learn How >
FedEx-Dane County Regional Airport Project
FedEx-Dane County Regional Airport Project
Learn How >
IQHQ-Research and Development District Project
IQHQ-Research and Development District Project
Learn How >
Greenwood Wastewater Main Repair Project
Greenwood Wastewater Main Repair Project
Learn How >
Brazoswood Athletic-High School Project
Brazoswood Athletic-High School Project
Learn How >