St. Joseph Hospital Expansion

Tampa, Florida

OWNER

BayCare

GC

Robins & Morton

REVENUE

$510,000

TIME

2018-2019

module background 2
GRIFFIN DIFFERENCE

Griffin tested design assumptions to verify system performance. Due to changed site conditions, Griffin modified the system during installation to achieve drawdown. The dewatering system was installed, with the new design, within the allotted contract time, allowing construction to proceed on schedule.

THE CHALLENGE

An engineered dewatering solution was required to lower groundwater below the proposed 26 ft. deep excavation during the Hospital expansion project. Significant loss of circulation was shown in the limestone underlying the site, which could contribute very high flows to the dewatering effort.

THE SOLUTION

Griffin designed a high-capacity deep well dewatering system to assist in the control of groundwater. Upon partial installation, Griffin performed a pump test to verify design assumptions.

The pump test showed no contribution from the underlying limestone. Due to the low permeability of the sand, the dewatering approach was modified to a perimeter wellpoint system.

CALCULATOR

DEWATERING ADVISOR

Enter your excavation information to learn about options and considerations for selecting dewatering systems.

CASE STUDIES

VIEW RELATED POSTS

Santa Ana Mainstream-Reach 9
Santa Ana Mainstream-Reach 9
Learn How >
West Refueler and Solid Waste Facility
West Refueler and Solid Waste Facility
Learn How >
Alexan Old Town Project
Alexan Old Town Project
Learn How >
Port Covington
Port Covington
Learn How >
929 Zurich Circle
929 Zurich Circle
Learn How >
L-611 Drainage Structure
L-611 Drainage Structure
Learn How >
Fort Eustis Sump Pit Structure
Fort Eustis Sump Pit Structure
Learn How >
Chesapeake City WWTP
Chesapeake City WWTP
Learn How >
Decatur School Annex
Decatur School Annex
Learn How >