Fort Eustis Sump Pit Structure Project

Newport News, Virginia

OWNER

US Army Corps of Engineers

TIME

2020

module background 2
GRIFFIN DIFFERENCE

Griffin successfully installed the dewatering system and achieved the required drawdown while maintaining communication and excellent relations with the client.

THE CHALLENGE

The typical scenario of layed river and or marine deposits creating interfacial conditions and SP soils capable of higher flows.

THE SOLUTION

Griffin employed wellpoints on proper centers to accommodate the flow and the required drawdown. Griffins experience to properly install the wellpoint equipment to achieve maximum performance.

CALCULATOR

DEWATERING ADVISOR

Enter your excavation information to learn about options and considerations for selecting dewatering systems.

CASE STUDIES

VIEW RELATED POSTS

Westminster Sewer Improvements Project
Westminster Sewer Improvements Project
Learn How >
West Refueler and Solid Waste Facility Project
West Refueler and Solid Waste Facility Project
Learn How >
University of Nebraska-Kiewit Hall Project
University of Nebraska-Kiewit Hall Project
Learn How >
The Yards Parcel I Project
The Yards Parcel I Project
Learn How >
The Driscoll at River Oaks High-Rise Project
The Driscoll at River Oaks High-Rise Project
Learn How >
Texas Medical Center Project
Texas Medical Center Project
Learn How >
St. Joseph Hospital Expansion Project
St. Joseph Hospital Expansion Project
Learn How >
SLC Airport Central Tunnel Project
SLC Airport Central Tunnel Project
Learn How >
Seabrook Gate Complex, CMAR Project
Seabrook Gate Complex, CMAR Project
Learn How >
Saylorville Lake/Big Creek Dam Project
Saylorville Lake/Big Creek Dam Project
Learn How >