Mill Creek Diversion Chamber Project

Cincinnati, Ohio

ENGINEER

Burgess & Niple Engineering

TIME

2020- 2021

D.CaseStudies Mill Creek Geottle Web 1
Griffin Difference

Griffin’s Engineering and Design Team provided a design that lowered the piezometric groundwater level to the required depth. Griffin’s Operation Team worked long hours to install the system, some days up to 16 hours and on weekends to meet the mutually agreed schedule.

We also worked closely with other sub-contractors and the Contractor on design changes, including the placement of three additional wells in manhole structures. All work was completed within an aggressive schedule and portions were able to help toward the MBE/WBE requirements of the project.

THE CHALLENGE

Winter installation next to Mill Creek that required drilling through an upper layer of Urban Fill to a depth of 100’ +/- in high permeability soils. The performance-based design involved relieving hydrostatic pressures to a depth of 63’ below ground surface. The site required two discharge locations and burial of some of the discharge piping.

THE SOLUTION

Griffin provided turnkey drilling and installation operations for the deep well system. Due to difficulty drilling through the urban fill a specialized drilling subcontractor was utilized to drill the upper portion of each well. The high flows required 24” HDPE discharge piping and flow meters to monitor the flow rates for reporting.

CALCULATOR

DEWATERING ADVISOR

Enter your excavation information to learn about options and considerations for selecting dewatering systems.

CASE STUDIES

VIEW RELATED POSTS

Westminster Sewer Improvements Project
Westminster Sewer Improvements Project
Learn How >
West Refueler and Solid Waste Facility Project
West Refueler and Solid Waste Facility Project
Learn How >
University of Nebraska-Kiewit Hall Project
University of Nebraska-Kiewit Hall Project
Learn How >
The Yards Parcel I Project
The Yards Parcel I Project
Learn How >
The Driscoll at River Oaks High-Rise Project
The Driscoll at River Oaks High-Rise Project
Learn How >
Texas Medical Center Project
Texas Medical Center Project
Learn How >
St. Joseph Hospital Expansion Project
St. Joseph Hospital Expansion Project
Learn How >
SLC Airport Central Tunnel Project
SLC Airport Central Tunnel Project
Learn How >
Seabrook Gate Complex, CMAR Project
Seabrook Gate Complex, CMAR Project
Learn How >
Saylorville Lake/Big Creek Dam Project
Saylorville Lake/Big Creek Dam Project
Learn How >