Griffin installed the dewatering system on schedule and withing budget. Griffin continued to monitor the dewatering system throughout the project and made sure contractor was operating and maintaining the system properly.

THE CHALLENGE

Lowering groundwater 15 ft. below ground surface for an excavation of approximately 250 ft x 50 ft.

THE SOLUTION

A wellpoint dewatering system was installed surrounding the proposed excavation’s approximately 600 ft. perimeter. Griffin installed 85 wellpoints at approximate spacing of 7 ft. to a depth of 30 ft. One operating and one standby wellpoint pump were utilized for the project.

CALCULATOR

DEWATERING ADVISOR

Enter your excavation information to learn about options and considerations for selecting dewatering systems.

CASE STUDIES

VIEW RELATED POSTS

Westminster Sewer Improvements Project
Westminster Sewer Improvements Project
Learn How >
West Refueler and Solid Waste Facility Project
West Refueler and Solid Waste Facility Project
Learn How >
University of Nebraska-Kiewit Hall Project
University of Nebraska-Kiewit Hall Project
Learn How >
The Yards Parcel I Project
The Yards Parcel I Project
Learn How >
The Driscoll at River Oaks High-Rise Project
The Driscoll at River Oaks High-Rise Project
Learn How >
Texas Medical Center Project
Texas Medical Center Project
Learn How >
St. Joseph Hospital Expansion Project
St. Joseph Hospital Expansion Project
Learn How >
SLC Airport Central Tunnel Project
SLC Airport Central Tunnel Project
Learn How >
Seabrook Gate Complex, CMAR Project
Seabrook Gate Complex, CMAR Project
Learn How >
Saylorville Lake/Big Creek Dam Project
Saylorville Lake/Big Creek Dam Project
Learn How >