Griffin Difference

Despite the seasonal variability in the groundwater table, Griffin stood out due to our quick response for the design and installation of a dewatering system. This also ensured the successful installation of the sanitary sewer line prior to the arrival of the high ground water seen in this area, thus saving the contractor significant costs.

THE CHALLENGE

Groundwater had to be lowered 12′-18′ below ground surface for the new sanitary sewer. Due to the high flow rates the discharge water from the system had to be placed far enough away from the excavation to prevent recharge as well as not flood adjacent properties

THE SOLUTION

Griffin installed a system consisting of 8 deep wells approximately 60 ft. on center for
the sanitary sewer to a depth of 40′, 1200LF of 16” HDPE discharge piping, and
30HP pumps. During the progression of the project select wells were tuned on and off
thus lowering the groundwater for their excavation while limiting the amount of water
that was being discharged.

CALCULATOR

DEWATERING ADVISOR

Enter your excavation information to learn about options and considerations for selecting dewatering systems.

CASE STUDIES

VIEW RELATED POSTS

Westminster Sewer Improvements Project
Westminster Sewer Improvements Project
Learn How >
West Refueler and Solid Waste Facility Project
West Refueler and Solid Waste Facility Project
Learn How >
University of Nebraska-Kiewit Hall Project
University of Nebraska-Kiewit Hall Project
Learn How >
The Yards Parcel I Project
The Yards Parcel I Project
Learn How >
The Driscoll at River Oaks High-Rise Project
The Driscoll at River Oaks High-Rise Project
Learn How >
Texas Medical Center Project
Texas Medical Center Project
Learn How >
St. Joseph Hospital Expansion Project
St. Joseph Hospital Expansion Project
Learn How >
SLC Airport Central Tunnel Project
SLC Airport Central Tunnel Project
Learn How >
Seabrook Gate Complex, CMAR Project
Seabrook Gate Complex, CMAR Project
Learn How >
Saylorville Lake/Big Creek Dam Project
Saylorville Lake/Big Creek Dam Project
Learn How >