Santa Ana Mainstream-Reach 9 Project

Yorba Linda, California

CLIENT

Government

OWNER

Silverstrand Construction

PROJECT REVENUE

$1,260,000

TIME

2021

D.CaseStudies Reach 9 Site Photo WEB
GRIFFIN DIFFERENCE

Griffin successfully installed the dewatering system and achieved the required drawdown while maintaining communication and excellent relations with the client.

THE CHALLENGE

The overall work scope included grouting of an existing pipeline bedding rock which proved to be a challenge. Extensive sumping efforts were needed to eliminate any perched water.

THE SOLUTION

Installation of a deep well system along the excavation alignment in conjunction with a wellpoint system to achieve drawdown and mop up any perched or standing water.

Grouting will be required to plug up the pipeline bedding rock, which acts as a conduit allowing ground water to infiltrate into the work zone.

CALCULATOR

DEWATERING ADVISOR

Enter your excavation information to learn about options and considerations for selecting dewatering systems.

CASE STUDIES

VIEW RELATED POSTS

Avenue O Building D Project
Avenue O Building D Project
Learn How >
University of Nebraska-Kiewit Hall Project
University of Nebraska-Kiewit Hall Project
Learn How >