Dakota Range III Wind Farm Project

Summit, South Dakota

CLIENT

Wanzek Construction

OWNER

Dakota Range III, LLC

ENGINEER

Barr Engineering

TIME

2020

REVENUE

$112,000

D.CaseStudies dakota range wind
GRIFFIN DIFFERENCE

Griffin was asked to review the geotech and design a dewatering system, provide and operate the machines to install the system, then remobilize, remove, and reinstall the system for an additional site. Not to mention mobilize a 3rd time to remove and return the system upon final completion. Griffin also provided remote telemetry that was able to monitor groundwater flows and transmit that data offsite 24/7, ensuring the system was always running. Few dewatering companies can provide such services in such a quick and efficient timeframe that was required by Wanzek.

THE CHALLENGE

The biggest challenges of this project were the access to each foundation was remote, so roads had to be constructed to get to each location through farm fields. After access was provided, the soil profile proved to be littered with cobbles making jetting very difficult.

THE SOLUTION

Since the foundation sites are remote, getting an ample water supply is key in getting the system installed quickly and efficiently. Since the excavations had already been attempted without dewatering, a large amount of groundwater was present in the already open excavation. We pumped the water directly from this reservoir of groundwater and used this water for the jetting, expediting jetting and not having to haul water to the site. We saved time by using the Griffin Track Punch jetting tool, and installed wellpoints through the cobbly soils, without having to ship a drill rig to the site. Both items made the install quick, efficient, and economical for the customer.

CALCULATOR

DEWATERING ADVISOR

Enter your excavation information to learn about options and considerations for selecting dewatering systems.

CASE STUDIES

VIEW RELATED POSTS

Santa Ana Mainstream-Reach 9 Project
Santa Ana Mainstream-Reach 9 Project
Learn How >
West Refueler and Solid Waste Facility Project
West Refueler and Solid Waste Facility Project
Learn How >
Alexan Old Town Project
Alexan Old Town Project
Learn How >
Port Covington Project
Port Covington Project
Learn How >
929 Zurich Circle Project
929 Zurich Circle Project
Learn How >
IAA Project
IAA Project
Learn How >
L-611 Drainage Structure Project
L-611 Drainage Structure Project
Learn How >
Fort Eustis Sump Pit Structure Project
Fort Eustis Sump Pit Structure Project
Learn How >
Chesapeake City WWTP Project
Chesapeake City WWTP Project
Learn How >
Decatur School Annex Project
Decatur School Annex Project
Learn How >