Greenwood Wastewater Main Repair Project

Corpus Christi, Texas

OWNER

Texas Department of Transportation

CLIENT

Clark Pipeline Services

ENGINEER

Freese & Nichols

REVENUE

$73,000

TIME

2020

D.CaseStudies Greenwood final
GRIFFIN DIFFERENCE

Griffin installed the eductor wells utilized a low-clearance drill rig capable of drilling under limited height conditions. In addition, the eductor system’s unique ability to put a vacuum on the soil at much greater depths than a standard wellpoint provided dewatering and stabilization for the deep excavation.

THE CHALLENGE

Lowering groundwater 25 ft. below ground surface was needed for an excavation of approximately 120 ft. x 15 ft. The existing 48-inch wastewater line was under TX State Highway 358 with limited overhead clearance to install the dewatering system.

THE SOLUTION

An eductor dewatering system approximately 120 ft. long was installed parallel to one side of the existing line. Griffin installed 15 eductors at the approximate spacing of 10 ft. to a depth of 45 ft. In addition, we provided one operating and one standby eductor pump to eliminate the risk of system downtime.

CALCULATOR

DEWATERING ADVISOR

Enter your excavation information to learn about options and considerations for selecting dewatering systems.

CASE STUDIES

VIEW RELATED POSTS

Santa Ana Mainstream-Reach 9 Project
Santa Ana Mainstream-Reach 9 Project
Learn How >
West Refueler and Solid Waste Facility Project
West Refueler and Solid Waste Facility Project
Learn How >
Alexan Old Town Project
Alexan Old Town Project
Learn How >
Port Covington Project
Port Covington Project
Learn How >
929 Zurich Circle Project
929 Zurich Circle Project
Learn How >
IAA Project
IAA Project
Learn How >
L-611 Drainage Structure Project
L-611 Drainage Structure Project
Learn How >
Fort Eustis Sump Pit Structure Project
Fort Eustis Sump Pit Structure Project
Learn How >
Chesapeake City WWTP Project
Chesapeake City WWTP Project
Learn How >
Decatur School Annex Project
Decatur School Annex Project
Learn How >