R M Schaeffer Piping Redirect Project

Wheatfield, Indiana

OWNER

Graycor Construction

ENGINEER

NIPSCO

TIME

2020

REVENUE

$400,000

D.CaseStudies RM Shaeffer
GRIFFIN DIFFERENCE

Griffin had prior experience at the project site and knew what it would take to get the job done. Flexibility with installation techniques provided the most cost-effective solution.

THE CHALLENGE

Numerous excavations requiring dewatering systems that varied from 30 ft. jetted deep wells to jetted wellpoint systems. Wells could not be installed by drilling due to the high water table.

THE SOLUTION

Installation by jetting with the Griffin Track Punch Jetting Tool for both the deep wells and wellpoints alleviated the challenges typically associated with installing wells in an area with a high water table.

CALCULATOR

DEWATERING ADVISOR

Enter your excavation information to learn about options and considerations for selecting dewatering systems.

CASE STUDIES

VIEW RELATED POSTS

Santa Ana Mainstream-Reach 9 Project
Santa Ana Mainstream-Reach 9 Project
Learn How >
West Refueler and Solid Waste Facility Project
West Refueler and Solid Waste Facility Project
Learn How >
Alexan Old Town Project
Alexan Old Town Project
Learn How >
Port Covington Project
Port Covington Project
Learn How >
929 Zurich Circle Project
929 Zurich Circle Project
Learn How >
IAA Project
IAA Project
Learn How >
L-611 Drainage Structure Project
L-611 Drainage Structure Project
Learn How >
Fort Eustis Sump Pit Structure Project
Fort Eustis Sump Pit Structure Project
Learn How >
Chesapeake City WWTP Project
Chesapeake City WWTP Project
Learn How >
Decatur School Annex Project
Decatur School Annex Project
Learn How >